The Burgin Residence

  • Completion of level 1 transfer slab
  • Stripping of the basement levels has commenced
  • Erection of the external perimeter scaffolding has commenced
  • Heritage rectification works have commenced
  • Basement rough in has commenced.
  • Formwork on level 3 has commenced.