The Burgin Residence

  • The Burgin Residence hit the milestone mark of topping out the structure in September
  • The fitout trades are progressing well with commencement of the kitchen and bathroom joinery early October for level 1 and the final strip out of the formwork to level 7.
  • All the trades are now hitting there 6 day cycles and pushing on through the floors with the windows about to commence level 6 this week.
  • The cladding is complete, up to level 5 and ready for inspection prior to the scaffold being dismantled in the coming weeks where the project will be unveiled to the local community.
  • The next period will be a very exciting time for all involved as we will start to complete level 1 and see the final building without being clad in scaffold.